Greenwood Drive Full Opening Delayed

Due to a problem with newly installed water main pipes, the full opening of Greenwood Drive, near the Route 8 intersection, has been delayed until the end of October / early November.

While the majority of the pipe work has been completed, and only three houses need to be connected to the new system, the new water main pipes did not pass their final inspection. 

Water leaks were detected during pressure testing, and as a result, the contractor will have to dig up some pipe for further investigation.

Crews will do their best to work around this delay by sequencing the installation of curbing and road paving.  Homes in the area will remain connected to the temporary water system.